Susquehanna River Rail Bridge Project

For more information, including community engagement schedules, program updates and additional resources, visit AmtrakNewEra.com/SRB

Quick Facts: Susquehanna River Rail Bridge

Project Status

Construction contract awarded and final design underway

Customer Benefits

  • Increases passenger rail capacity by replacing the existing 2-track bridge with four total tracks across two new bridges
  • Modernizes rail infrastructure including track, overhead catenary/power and signals
  • Improves reliability and safety
  • Increases train speeds and decreases trip times
  • Eliminates conflicts with maritime traffic

Estimated Construction Completion

2036

Latest Milestones

  • Awarded the major construction contract and two supporting contracts in late 2023

Upcoming Milestones

  • Summer 2024: Begin remnant pier removal
  • Late 2024: Complete 100% design
  • 2025: Begin major construction

Project Partners

Federal Railroad Administration (FRA), Maryland Department of Transportation Maryland Transit Administration (MDOT MTA)

Funding Sources

Fully funded by FRA Federal-State Partnership – NEC Grant Program (Awarded November 2023), State of Maryland, Amtrak

 

Workforce

Flatiron - Herzog JV

Amtrak’s Susquehanna River Bridge is a two-track, swing-span rail bridge that was built in 1906 and is located in the City of Havre de Grace in Harford County, MD, and the Town of Perryville in Cecil County, MD.

This aging bridge is a bottleneck along a critical link of the Northeast Corridor (NEC), one of the busiest and economically vital transportation systems in the world. The bridge’s swing span must be opened manually by up to 30 personnel to allow taller marine traffic to pass, which causes disruptions to both rail and marine operations. The outdated design of the existing bridge requires passenger trains to slow down to 90 mph and freight trains to 30 mph or less as they cross over the Susquehanna River with speeds up to 125 mph adjacent to the bridge. Due to the two-track design, trains must reduce speed even further or stop on the bridge when crossing to their final destination.

The Susquehanna River Bridge Project will replace the existing bridge with two new parallel, fixed-span structures featuring a total of four tracks that will improve capacity, trip time and safety for commuter, freight and intercity passenger rail services. The new structures will allow passenger trains to travel at high speeds on this part of the NEC. The NEPA environmental review for the project has been completed and the advanced design phase began in 2017. Amtrak selected a construction contractor in late 2023 and kicked off the project in the Summer of 2024. This roughly $2.7 billion project is supported by a Federal-State Grant and additional funding by Amtrak and the State of Maryland.

For project updates sign up for our newsletter 

Additional Resources

Environmental Studies

For more information, take a look at the documents detailing the Environmental Assessment and Draft 4(f) Evaluation, and the Finding of No Significant Impact (FONSI).

We Want to Hear From You

The Environmental Assessment has concluded, but we'd still like to hear from you if you have any questions.
Email us at SRBProject@amtrak.com or call 844-SUS-RAIL (844-787-7245).

 

Every ride counts as an Amtrak Guest Rewards member. Earn points toward reward travel, upgrades and more.

Guest Rewards